Both Engines Running

Success at last! Both engines are now running and we broke six mega watts of daily production on December 13th 2010.
At this time the ramp up to full power is about two weeks ahead of schedule. This is due to the increase of FOG concentrates and ORRs waste.

The Anaerobic Digester is now completely on veal manure and what seemed to be a challenge at the start of the project has turned out to be a source of excellent CH4 gas. The increase to 500 KWH should be completed by mid February and this continued increase will be the result of ORMI‘s mixtures of FOG and ORRs.

Here is some background on ORMI and where and how they get the materials that boost Anaerobic Digester performance.